Civil and Enabling Works to commence from March
Seqwater has awarded the construction contract for the East Bank Flood Resilience Program (EBFRP) Civil and Enabling works to McIlwain Civil Engineering Pty Ltd. https://mcilwain.com/
The Civil and Enabling works project involves earthworks, construction of a mass block retaining walls, new substation pad, provision of a new sealed access road to the new substation pad, upgrading the Eastern Access Road including conduit installation and reconfiguration of the six-way intersection. Work for this component of the EBFRP is scheduled to commence work from March 2022. Read more about the construction phase here.
The completion of this EBFRP Civil and Enabling Project will allow Energex to commence the construction of the new Substation.