Work will start at the Linville Water Treatment Plant on Monday 2 September 2019.

The new $2 million plant will deliver a more reliable, effective drinking water supply to the 400-plus residents of Linville.

The existing plant, which was constructed in 1970, was forced to close after the 2013 floods put the facility out of action. 

Seqwater will continue to tanker in drinking water from the nearby Kilcoy Water Treatment Plant until the new plant is operating.

The project is expected to take up to six months to complete, subject to weather conditions, with the new plant operational by early 2020.

The new plant will be larger and house an improved water quality monitoring station, which will draw on water locally.

It will also have upgraded filters and ultraviolet (UV) disinfection capabilities for added protection.

Seqwater will work closely with residents during demolition and construction to minimise any disruptions. 

For more information please contact us on 1300 SEQWATER (1300 737 928) or email communications@seqwater.com.au